This tutorial focuses on installing J-trim around the soffit area of an eave extension as part of a Worldwide Steel Buildings kit. The J-trim provides a receiving channel and finished border for the soffit panels beneath the extension. It highlights continuous alignment, corner transitions, and preparation for a clean soffit installation, helping DIY builders and installation crews understand how this step fits into the overall construction sequence.
What You'll Learn
- How to create the soffit receiving perimeter
- How to align J-trim around the eave extension
- How to prepare corners for soffit-panel installation
Video Transcript
If your building has a sidewall extension, J-Trim will need to be placed along the wall. This will allow the soffit panels to slide into place.
J-Trim will be identified on your sheet metal trim package list as at eave extension soffit.
The J-Trim will span from end to end of your extension.
Although each piece of trim is 10 feet 2 inches long, it has a coverage of 10 feet. As you install additional pieces of trim, they should lap the previous piece by a minimum of 2 inches.
Use a level and a pencil to mark your J-Trim install location along your wall. This will ensure your J-Trim is flush with the bottom leg of your low eave purlin.
Before installing J-Trim, place your outside foam closure strips along the wall panels, following the marks you made earlier.
These are critical for sealing out moisture and pests.
Check each piece with a level as you go.
When you reach the end of your sidewall, remove any excess foam closure material with a knife or razor blade.
Once closures are in place, install the J-Trim on top of the foam closure strips, starting at the bird box with a 2-inch overlap as demonstrated here.
Each length of J-Trim should be secured with a minimum of 3 sheet metal screws into the high rib of the wall panels.
As you lap additional pieces of trim, ensure the lap has a sheet metal screw securing both pieces through the high rib of the wall panel.
It’s critical that the J-Trim runs straight. Check every piece as you go with a level.
Once all the J-Trim is installed, you may install your sidewall extension soffits.