Video Description
This tutorial focuses on installing purlins across the overhang framing as part of a Worldwide Steel Buildings kit. These members support the roof panels over the projected area and tie the overhang trusses together. It highlights consistent spacing, straight alignment, and secure attachment across the extension, helping DIY builders and installation crews understand how this step fits into the overall construction sequence.
What You'll Learn
- How to install purlins across the overhang trusses
- How to maintain spacing and straight alignment
- How the purlins support the projected roof panels
Video Transcript
Now that your overhang trusses are in place, it’s time to install your purlins.
Purlins are the secondary members that will make up the roof of your building.
It is important to note that in this example, we are using World Wide Steel Building’s web truss columns and roof trusses with 6-inch purlins on the roof and 3 5/8ths-inch girts on all walls.
If your building kit has different components than noted, then the dimensions you will need to use may vary from this video.
Please be sure to verify the dimensions against your W drawings.
The placement of purlins is important to ensure that the overhang trusses are not leaning in or out, so please make sure that you have the correct purlin for each location by referencing your W drawings and your ship list.
On the galvanized secondary framing list, you will have the location or use for each secondary member.
Locate the secondary members that indicate they are purlins for the bay you are currently installing.
In this example, starting at grid one on your W drawings, the 1st frame is set 6 5/8ths inches back from the end wall.
For buildings with no gable extension, each purlin that is installed in the bay between grids one and 2 is marked at 6 5/8ths inches from the end of the purlin.
This mark should line up with the center of the preinstalled welded clip on top of your grid one overhang truss.
Attach with 4 number 12 Tek screws as shown here.
If your building has a gable extension, you will need to add the extension length onto this 6 5/8ths-inch dimension prior to marking. For example, if you have a one foot 0 inch gable extension noted on your W1 drawing, you will need to add the one foot 0 inches to the 6 5/8ths-inch dimensions, which is a total of one foot, 6 5/8ths inches.
Measure this distance from the end of the purlin and make a mark for the center of the welded clip as shown here.
Do this for each purlin required in the bay you are installing.
Once your marks have been made, line it up along the center of the preinstalled clip of your overhang truss.
It is a good idea to utilize a locking C-clamp to hold the purlin in place at each end before attaching it to the clip using 4 number 12 Tek screws as shown here. The C-clamp can be removed once the Tek screws are installed.
Attach the other end of the purlin to the adjacent overhang truss, making sure the purlin lines up in the center of the truss.
Because the purlin stops at the center line of the 2nd truss’s preinstalled clip, you will only use 2 Tek screws to install.
When you have an intermediate bay where neither truss you are installing purlins on are the last frame in your building, then each end of your purlin will line up with the center line of the preinstalled clip, and each end will only require 2 Tek screws to install.
Once all overhang purlins have been installed, it’s time to install the nested eave purlin at overhang.