Low Eave Purlin with Eave Extension

Video Description

This tutorial focuses on installing the low-eave purlin when the building includes an eave extension as part of a Worldwide Steel Buildings kit. The extended configuration requires the purlin and projection framing to work together at the roof edge. It highlights the relationship between the main roof, extension framing, soffit area, and exterior trim, helping DIY builders and installation crews understand how this step fits into the overall construction sequence.

What You'll Learn

  • How the low-eave purlin fits an extended roof edge
  • How the main roof and extension framing connect
  • How to prepare the edge for soffit and finish trim

Video Transcript

Now that your eave extensions are installed, it is time to install your eave purlin at the exterior wall line.

This purlin will be the top connection for your wall panels, so it is extremely important that when installed, the outside face of this eave purlin is in line with the outside edge of your sidewall girt line. This will ensure the wall panels are installed in one continuous plane and you don’t have the top of your wall panels bowing inward or outward from your girts.

Your roof panel will also attach to this eave purlin, so once it is in line with your girts, you will need to adjust the eave purlin vertically so that the top outside edge is in plane with the top of your building purlins.

Your eave extension should have a pre-welded clip where this eave purlin at wall should be located.

Because the eave purlin connects in between 2 eave extensions, you will need to measure each purlin.

In this example, our distance between the extensions is 88 and one-eighth inches.

Measure this distance on your eave purlin and cut it to length.

When cutting the eave purlin at your end wall frame, you will need to keep the cut off purlin, as it will attach on the outside of the eave extension at the end wall frame to be able to support your wall panels out to the corner of your building. We will show more on this here in a bit.

Because the purlin attaches in between the 2 eave extensions, you will need to notch the top and bottom legs of the purlin in order to miss the top and bottom flanges of the eave extension when installed.

On the top and bottom legs, measure out approximately one inch from the end of the purlin. Mark this distance on the leg and down the web face of the purlin.

Then measure up the web approximately one inch from both the top and bottom legs of the purlin and draw a line to the end of the purlin.

Cut out the notches drawn at the top and bottom of the purlin.

Place the eave purlin in place and clamp each end to the pre-welded clip on the eave extension.

Using a piece of galvanized secondary, you can line up the outside of your girts with this eave purlin as shown. If the eave purlin needs adjustment to line up with the girts, you need to loosen the bolt securing the eave extension and slide the eave extension up or down slope until your eave purlin is in line with your girts. Then tighten up the bolts holding the eave extension.

You now need to ensure that the top outer edge of your eave purlin is in plane with the top flanges of the rest of your purlins.

Place a piece of galvanized secondary across the roof purlins and extend it down to the eave purlin.

Loosen the clamp and adjust the eave purlin vertically until the outside top corner is in plane with the top of the purlin.

Reinstall the clamp once your adjustments have been made.

You are now ready to install the tek screws that will attach the eave purlin to the pre-welded clips.

When installing an eave purlin at wall with an eave extension at your end wall frame, you need a short piece of eave purlin that will attach on the end wall side of your eave extension.

By referring to your W1 drawing, the center line of our end wall column is 6 and five-eighths inches from the outside edge of slab. Since our building has a gable extension, we will need to add the gable extension dimension of one foot 0 inches to the 6 and five-eighth inch measurement. This means that the dimension from the center line of the roof truss to the end of the eave purlin is one foot 6 and five-eighth inches. Measure, cut, and install using 2 tek screws into the eave extension on the end wall frame.

The other end of this eave purlin will be secured when installing the gable track at the ends of the purlins.

Got a Question?

Contact us to get started on your own steel building.

View SMS Terms & Conditions

By opting into SMS from a web form or other medium, you are agreeing to receive SMS messages from Worldwide Steel Buildings. This includes SMS messages for appointment scheduling, appointment reminders, post-visit instructions, lab notifications, and billing notifications. Message frequency varies. Message and data rates may apply. See privacy policy at https://www.worldwidesteelbuildings.com/privacy-policy/. Message HELP for help. Reply STOP to any message to opt out.

‹ Previous Video

Eave Extension Install

Next Video ›

Soffit J-Trim Installation at Eave Extension

Testimonials

Real Stories. Real Results.

Posted on Google Google
Zach Zaroor profile picture
Zach Zaroor
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
I worked with Jayson in sales. Told him what we were looking for, plans changed, and he quickly adapted with them. He was helpful, always answers the phone, and is willing to walk you through anything in further detail that you need. I will be using not only Jayson, but Worldwide Steel Buildings again in the future.
Posted on Google Google
Clayton Ericson profile picture
Clayton Ericson
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Worked with Wendy on our project, she was very helpful from start to finish. Decided on a 24 x 36 hybrid building. The building went up without any real problems. If i did have any questions she was right there to answer my questions. I chose the hybrid version with wood purlins. This saved me about $2500 and made it easier to assemble by myself. Im very happy with my shop and have had no issues with it. Wendy made my project easier with her knowledge and help. Dean E.
Posted on Google Google
MattNC Video profile picture
MattNC Video
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Great experience with WWSB and Wendy Wickenhauser in the process of designing, ordering and receiving my custom shop design. I was very pleased with the entire process, communication and product delivered. I built it myself and the included guidebook was also extremely helpful.
Posted on Google Google
Susan Bowers profile picture
Susan Bowers
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
We are extremely satisfied with our Worldwide steel building. Wendy was very helpful with the design and making sure we thought about all options. Wendy and all the tech people were very helpful during the construction phase, which we did ourselves. I’m sure that sometimes our techniques were not OSHA approved, but no body died! lol.
Posted on Google Google
Krystal Burrows profile picture
Krystal Burrows
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
I’ve had a great experience working with Jerad Henry on my metal building project. He has spent hours with me going through the design and functionality of the building, answering questions, and offering insights I honestly wouldn’t have thought of on my own. His knowledge and patience made the entire process smooth and stress-free, and it’s clear he genuinely cares about getting the building right for my needs. It’s been a pleasure working with Jerad Henry, and I’m really looking forward to receiving and building the building.
Posted on Google Google
Bayou Construction & Consultants profile picture
Bayou Construction & Consultants
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
As a General Contractor, who has been building structures around the world, working with Jerad Henry and the team of professionals here at Worldwide Steel Buildings has been a fresh air experience. Jerad has made easy for us to provide great structures for clients from here in Texas to Colorado to South Carolina. The mixture of his dedication to the clients to his manufacturing team design and construction of the buildings to seamless delivery to the job site, has made our crews lives easy and efficient. Here is to our continued future working together. Thanks!!!
Posted on Google Google
Melissa 'Missy' Mihelich profile picture
Melissa 'Missy' Mihelich
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Jerad is an absolute gem! He has worked and helped us so much with our building... basically a Barndominium. Only positive experiences and thank you!
Posted on Google Google
Matt Brown profile picture
Matt Brown
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Wendy and the entire staff at World Wide were great to work with. I was very pleased with the customer service and building quality

Not Sure Which Roof System Is Right for Your Building? We can help!

Our team can help you compare roof system options based on your building use, budget, location, and desired appearance.

Back To Top