Video Description
This installation video covers installing the lower horizontal girts across the endwall during the steel-building assembly process. The lower girts create attachment points for wall panels and connect the endwall columns near the base of the structure. Viewers are introduced to level placement, proper spacing, and integration with door or window openings, making the tutorial useful for both first-time DIY builders and experienced jobsite crews.
What You'll Learn
- How to position the lower endwall girts
- How to maintain level spacing across the endwall
- How to frame around planned doors and windows
Video Transcript
Now that your endwall columns have been placed, it’s time to install your lower endwall girts.
The lower endwall girts will be installed from the side wall girts to the endwall post or between endwall posts.
It is important to note that in this example, we are using World Wide Steel Building’s web truss columns and roof trusses with 6-inch purlins on the roof and 3 5/8ths-inch girts on all walls. If your building kit has different components than noted, then the dimensions you will need to use may vary from this video.
Please be sure to verify the dimensions against your W drawings.
When installing girts along the endwall of your building, it is important to make sure that you have the correct girt for each location.
Your W drawings and ship list will show you which girts should be used and where they should be placed in your building.
On the galvanized secondary framing list, you will have the location or use for each secondary member.
For the endwall girts, locate the necessary secondary members that indicate they are for FEW, front endwall, or REW, rear endwall, that pertain to the endwall you are working on.
If the girts are identified only as girts at endwalls, then these girts are used at both endwalls.
If you have an overhead door framed opening in your walls, then the length of the girts necessary to install will be shown on your W drawings. Refer to our overhead door framing installation video for additional information.
It’s a good idea to check the length of the girt prior to install.
In our example here, each endwall section is 10 feet 0 inches, and we have no overhead door openings in the walls. Therefore, we are using the girts that are 10 feet 0 inches in length.
Lift your girt into place.
The end of your endwall girt will overlap on top of your side wall girt and will be flush with the side wall girt edges as shown here.
Install 4 number 12 Tek screws through the endwall girt and into the return leg of the side wall.
The other end of your endwall girt will rest on the pre-welded girt clip on the endwall column.
Because the endwall girt stops at the center of the endwall column, you are only required to install 2 number 12 Tek screws as shown here.
On most buildings, the slope or pitch of the roof is high enough that you will reach a point where the girts will need to be cut and installed or nested into the endwall track that rests underneath the roof purlins.
Please proceed to the upper endwall girt installation video for your next steps.