Video Description
Learn the key considerations for installing track across the endwall framing in a Worldwide Steel Buildings project. The track creates a defined attachment point for endwall panels and helps establish a finished perimeter. The video emphasizes consistent placement, alignment with adjacent framing, and coordination with openings so builders can approach the work with a clearer understanding of the component and its place in the finished structure.
What You'll Learn
- How to position track across the endwall framing
- How to maintain a straight attachment line
- How the track supports panels around endwall openings
Video Transcript
Before installing your upper endwall girts, you must 1st install your endwall track.
The endwall track is required for endwall girt attachment.
It is important to note that in this example, we are using Worldwide Steel Building’s web truss columns and roof trusses with 6-inch purlins on the roof and three and five-eighths inch girts on all walls.
If your building kit has different components than noted, then the dimensions you will need to use may vary from this video.
Be sure to verify the dimensions against your W drawings.
Because our girts are three and five-eighths inches deep, we will use the track that is also three and five-eighths inches deep.
It is identified as the track at top of endwalls below purlins, as shown here on the ship list.
This track should be installed along the entire length of the endwall gable of the building, starting at the eave purlin and continuing up to the ridge purlin.
You may need to use multiple lengths of track depending on your building dimensions.
This track should not extend beyond the outside edge of the sidewall girts, as it will interfere with the wall panel installation.
If you do not have a gable extension, then the outside edge of the track will line up directly with the vertical face of the gable track previously installed.
If you do have a gable extension, then the outside edge of the track should align with the outside face of the endwall girts.
It is good practice to place a galvanized member vertically flat against the endwall girts as a guide.
Align the endwall track and clamp into place at your 1st purlin.
Additional clamps may be added at the eave purlin and the ridge purlin.
Install the track to the bottom side of the roof purlins with 2 number 12 Tek screws.
Continue installing Tek screws until the endwall track has been attached to each purlin.