Video Description
Learn the key considerations for installing the base girt along the bottom of the wall system in a Worldwide Steel Buildings project. The base girt establishes the lower support line for the wall panels and connects the wall framing near the foundation. The video emphasizes height, straightness, and a consistent attachment surface around the building perimeter so builders can approach the work with a clearer understanding of the component and its place in the finished structure.
What You'll Learn
- How to establish the lower wall-support line
- How to keep the base girt straight and level
- How the base girt supports the bottom of the wall panels
Video Transcript
The base girt of your building rests on top of the concrete slab and serves as the crucial base connection point for your building’s wall sheeting.
Your base girt will be the same galvanized secondary components that are used for your wall girts, as shown on the shipment list.
To anchor the base girt securely to the concrete foundation, you will need a minimum of a quarter-inch diameter by 2-inch-long concrete fastener, which are not supplied by Worldwide Steel Buildings.
In this example, we are using Worldwide Steel’s web truss columns with 3 and five-eighth inch wall girts.
When setting the columns, we had previously marked a chalk line at 3 and five-eighth inches from the edge of slab around the perimeter of the building.
This chalk line represents the outside face of our columns and the inside face of the building girts.
We are using this chalk line as a guide to place our base girts.
When setting the side wall base girt at the corner, you will need to know the location of your corner column from the end wall edge of slab. In our example, our building column sits 6 and five-eighths inches from the end wall edge of slab to the center line of the column.
Make a mark at 6 and five-eighths of an inch from the end of the base girt. This should line up with the center line of your column when set in place.
We recommend securing your base girts to the outside flange of the building column with clamps to avoid unintentional movement. And since the outside face of the column represents the inside face of the wall girt, clamping it down ensures it remains at the 3 and five-eighths inch measurement along your chalk line.
Depending on the quality of your concrete slab, the outside face of the base girt may or may not line up with the outside edge of your concrete down the length of a wall.
Concrete fasteners will be placed close to the middle of the base girt and on approximately 2-foot centers down the length of the base girt. Mark these holes with the aid of a tape measure.
Once marked, remove the base girt from the concrete before drilling holes so as not to damage your drill bit by contacting the concrete.
Proceed with drilling the required sized holes in your base girt.
Reposition the base girt and mark the corresponding holes on the concrete.
Then remove the girt and drill the holes into the concrete based on the concrete anchor recommendations.
For enhanced energy efficiency and protection against pests, it is recommended to apply sill sealer on top of the concrete before attaching the base girt.
This will ensure all gaps are sealed.
Place the base girt back onto the concrete and secure in place with the recommended concrete fasteners.
When installing the base girt at the corners, you will need to notch out the back leg of the end wall base girt to allow the 2 pieces of base girt to overlap in the corner, as shown here.
Since we are using 3 and five-eighth inch girts, we will measure, mark, and cut off the leg of the base girt at 3 and five-eighth inches.
Your notched base girt should slide under the overlapping base girt, as shown here.
In addition to clamps, we recommend using a single Tek screw to secure the overlapping corner base girts before marking your 2-foot centers.
Once marked, remove the base girt and repeat the drilling process previously shown, followed by marking the concrete, drilling the concrete,
applying the sill sealer at both sides of the corner,
placing your base girts,
resecuring your base girt with a clamp and Tek screw, and finally securing with concrete fasteners.
Follow this installation procedure for each bay that requires a base girt. Any openings in your building, such as overhead doors or walk doors, will not have a base girt installed.